VOC Test Report – Gym Remodel
Work #: 205018
Project Summary
Reason for inspection:
- Recent asbestos abatement during the gym remodel has caused odors and related concerns in the attached fine arts building.
Summary of concerns:
- None
Summary of recommendations:
- Establish negative pressure differential between gym and occupied spaces during remodeling and construction.
Observations and Data
FA3:
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:45.8% | Temp:65.4°F | CO2: 311 ppm | CO: 0 ppm |
FA3 (lab area):
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:45.9% | Temp:65.1°F | CO2: 328 ppm | CO: 0 ppm |
Corridor 1:
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:47.6% | Temp:65.2°F | CO2: 522 ppm | CO: 0 ppm |
Stairwell:
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:51.2% | Temp:46.0°F | CO2: 548 ppm | CO: 0 ppm |
Corridor 2:
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:47.8% | Temp:66.6°F | CO2: 536 ppm | CO: 0 ppm |
FA2:
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:45.4% | Temp:66.6°F | CO2: 508 ppm | CO: 0 ppm |
FA1:
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:47.5% | Temp:66.4°F | CO2: 444 ppm | CO: 0 ppm |
FA3A:
Summary: No Abnormal Findings
- tVOC levels @ 0ppb
| RH:44.6% | Temp:66.2°F | CO2: 352 ppm | CO: 0 ppm |